Construction update: the roof is on and windows are going in

Standard

The roofers have completed their work, except for the cupola on the garage, which is awaiting a weathervane; the windows are beginning to go in; and the house is getting wrapped.

In addition, the plumber is moving ahead on the rough-in, and we had the walk-through with the electrician this week. The electrical is pretty complicated, so the walk-through took more than four hours. Lots of outlets and switches.

It’s very exciting to see all the activity and all the trucks. I counted nine on Tuesday. The roofers cut the metal roofing on site and installed it. It was also fascinating to watch the workman ratchet themselves up on the scaffolding to install the upper windows.

House wrapped with several windows installed

House wrapped, with several windows installed

Garage, with roof

Garage, with roof

Windows waiting to be installed

Windows waiting to be installed

Guest shower

Guest shower

Workmen installing the living-room windows

Workmen installing the living-room windows

Living-room windows installed

Living-room windows installed

Advertisement

Discuss

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s